Sheet Piling Job Report
RaMeC Side – Grip against 25% – 100% Stronger End – Grip vibrators.
Job report of 800 000 m (2,4 milj. feet) Sheet-Piling job.
RaMeC SGV 90 | Exc. mountable vibrator | Crane suspensable vibrator | |
Excavator or Crane | Hyundai 330 | Hyundai 420 | Liebherr crawler crane |
Vibration power | 97 kW | 123kW | > 200kW |
Measured performance | 40 – 50m /hr | 20 – 22m / hr | 25 – 30m /h |
Straightness of the pile | very straight | problems in “R” direction | problems of X,Y,Z and “R” directions |
Manpower needed | 1 – 2 men | 4 – 5 men | 4 men |
Driving anchors | 12m (36f) anchor in 15 minutes – no problem | not possible | not possible |
Fulfilling safety regulations | yes | very much extra work needed | very much extra work needed |
ANCHORING at 45°